The Linz Café: Note accompanying signed original contract
01/01/1980
Contractual,
Notification
Sender:
Angela Hareiter, Forum Design: Österreichisches Institut für Visuelle Gestaltung, Linz, Austria
Recipient:
Christopher Alexander, Center for Environmental Structure , Berkeley, CA, U.S.A.
Medium:
Note
Language:
German
Download File
Content of
Project
Linz Café
1980
Linz , Austria
Commercial,
Realized
, Construction completed in Jul-1980
Client:
Forum Design; Österreichisches Institut für Visuelle Gestaltung - Angela Hareiter
C.E.S. staff:
Christopher Alexander
Contractor:
Construction management by the Center for Environmental Structure with local subcontractors
Project cost:
$35.000
Project stages:
Layout on the site by C.E.S. Use of full scale mock-ups Design Development drawings done after layout Direct construction management and on-site design decisions
Built as part of the international exposition "Forum Design" and designed to be "portable". Wooden building overlooking the Danube, with the first floor of the building raised to clear the ten-foot-high river embarkment. Yellow and red exterior, three stories, 2,300 ...
References
Reports
Linz Café: Unsigned contract for the design and construction of the Linz Café for the Design Forum exhibit
01/01/1980
Project,
Contractual,
Design and Construction Contract
Authors:
Christopher Alexander, Center for Environmental Structure, Berkeley, CA, U.S.A.
Language:
German
Unsigned copy of the contract between the Fonds der Hochschule für künstlerische und industrielle Gestaltung and Christopher Alexander.