C.E.S. Office – Martinez House: Construction Operations Manual

16/05/1980
Project Report

278-page document describing a sequence of building operations which were followed on the first two of the experimental structures built on the Martinez site, using the gunite techniques developed by the Center for Environmental Structure. These construction operations were named building “entities” or “wholes” and are described through field notes and the recording of the actual construction process applied. There are approximately 20 steps of operations followed on the 230 sq. ft. small workshop and 40 steps that were applied on the 1196 sq. ft. house; each step or operation consisted of a number of sub steps. .