House for Gail Kaiser and Mark Anderton: Construction Management Contract

22/03/1990
Contractual, Project Management Agreement

5-page signed construction management contract between the Center for Environmental Structure and Mark Anderson with Gail Kaiser, for the remodeling of their existing house. With an Appendix 3 with a breakdown of twenty one construction operations to be performed, and the analytical costs of each operation. Two more drafts of the contract are included.