Neighborhood of Five Houses: Modified Design Agreement
03/10/1992Signed 8-page design agreement between the Center for Environmental Structure and the clients, Linda and Geoffrey Gioja, Mike and Patricia Goddu, and Jim and Sylvia Heisey modifying their previous agreement of 22-May-1992. Three house designs will be made in consultation with each family, which will give each house unique qualities, using the same construction technique. The design and construction of all three will be on the same schedule.
References
-
Neighborhood of Five Houses: Superintendent Agreement
16/04/1994
Letter of Agreement between Carl Lindberg as Site Superintendent and C.E.S. Berkeley, as Construction Manager. Duties and position responsibilities are analyzed in detail.
-
Neighborhood of Five Houses: Agreement on Completion Procedure - Addendum to the Construction Contracts
01/12/1994
5-page unsigned draft agreement describing the completion procedure, meant to be included as addendum to the construction contracts. The points and steps pertaining to the completion of the project involve the Life Savings Bank as well. Outlines occupancy, house and ...
-
Neighborhood of Five Houses: Completion Agreement
15/12/1995
2-page letter of Agreement between the Center for Environmental Structure with Linda and Geoffrey Gioja, Sylvia and James Heisey, Patricia and Michael Goddu laying out the updated terms of completion, adjusted to the actual situation and to the specific demands ...