Julian Street Inn – Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place
1988Series of experiments and tests performed in the C.E.S. workshop in Martinez, for prefabricating wall-segment panels flat on the ground with the hand-glazed tiles, the required reinforcement and concrete layer, and then testing the procedure of lifting them in place. Ultimately, the process chosen was to glue the tiles on the plastered walls of the building on site, and then to fill in the gaps with grout.
Contents
-
The Julian Street Inn - Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place: Preparation notes
14/08/1987
Three pages of handwritten notes including a two-page cost estimate of materials needed for the five phases of production of the infill panels and one page of notes relating to the order of tiles and the costs of glazing and ...
-
The Julian Street Inn - Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place: Technical study
01/01/1988
It includes a 12-page draft study on the technical and structural requirements for the lifting process of the prefabricated wall-segment tile panels, and three pages with notes on the panel erecting and lifting-hardware .
-
The Julian Street Inn - Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place - Photographs of experimental mock-up depicting construction process
01/01/1988
Eight photographs of a full scale test tiled wall panel, the size and shape of an exterior wall segment with a window opening. They depict the procedure of its fabrication –placing tiles, placing and tiying reinforcement, and finally pouring and ...
-
The Julian Street Inn - Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place - Photographs of experimental mock-up depicting construction process
01/01/1988
Nine images from the process of moving the full scale prefabricated test tiled wall panel out of the workshop and lifting it, for testing its weight and behaviour. Finally the prefabrication of the tiled wall panels was rejected.
-
The Julian Street Inn - Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place - Photographs of experimental mock-up depicting construction process
01/01/1988
Four photographs of a full scale test tiled wall panel, the size and shape of an exterior wall segment with a window opening. They depict the first stage of its prefabrication procedure, during which tiles are laid out in relation ...