Julian Street Inn – Shelter for the Homeless: Construction experiments for testing the prefabrication of wall-segment tile panels and lifting them in place

1988
Construction System, Hand-glazed Tilework Panel
Series of experiments and tests performed in the C.E.S. workshop in Martinez, for prefabricating wall-segment panels flat on the ground with the hand-glazed tiles, the required reinforcement and concrete layer, and then testing the procedure of lifting them in place. Ultimately, the process chosen was to glue the tiles on the plastered walls of the building on site, and then to fill in the gaps with grout.
Created by:
Christopher Alexander, Gary Black
Contents