The Julian Street Inn – Shelter for the Homeless: General contractor’s letter forwarding fourteen proposed change orders, which being discretionary, do not allow a new contract total to be estimated, until the ones approved are agreed. Furthermore, he notifes the client that there is a list of eighteen items with cost estimates, which will be necessary to complete the job.
09/09/1988
References
-
The Julian Street Inn - Shelter for the Homeless: Change Order #9 issued by Oliver & Co.
09/09/1988
Change order reflecting the increase of the allowance for the cornice construction and closers.
-
The Julian Street Inn - Shelter for the Homeless: Change Orders #18 and #18a issued by Oliver & Co.
21/10/1988
Two change orders regarding kitchen plumbing works, each one describing items to be furnished and installed with relative costs. There is also an early version of the above referenced change orders, which is dated 9-Sep-88 and comprises both of the ...
-
The Julian Street Inn - Shelter for the Homeless: Change Orders #22 and #8rev issued by Oliver & Co.
20/12/1988
Two change orders referring to the dining hall; the first on raising wall height in accordance with drawings, and the second on roofing specifications. There is also an early version of change order #8, which is dated 9-Sep-88; initially proposed ...
SEE ALL Records