The Julian Street Inn – Shelter for the Homeless: Reminding Maxim Schrogin that the electrical, plumbing and heating drawings required by the contract, are past due. Sepia drawings must be reviewed by the architect first and prints must be distributed on site afterwards
23/05/1988
References
-
The Julian Street Inn - Shelter for the Homeless: Providing an overview of the 12-May-1988 meeting and laying out some of the specific issues discussed and approved by both, the architect, and the contractor
13/05/1988
-
The Julian Street Inn - Shelter for the Homeless: Addressing the issues mentioned in a previous letter regarding the heating and ventilation drawing. Notifying Maxim Schrogin that this letter will serve as architectural approval that the new marked up drawings are approved regarding aesthetic design
25/05/1988