The Jullian Street Inn – Shelter for the Homeless: A subcontract has been issued to Carl Lindberg within the budget allowance of Oliver & Company Inc.. Wishing that this can assure the completion of the arcade in accordance with everyone’s aesthetic and financial satisfaction
11/10/1988
References
-
The Julian Street Inn - Shelter for the Homeless: Discussing all unresolved yet design issues which considerably surpass the allowed budget and requesting redesigning and/or new bids to be made following the budget limits, all issues that are seriously delaying the construction. The overdue current payment to the contractor is also mentioned
28/09/1988
-
The Julian Street Inn - Shelter for the Homeless: Requesting from the Center for Environmental Structure to resume immediatelly its work according to the contract and resolve the issue of Carl Lindberg's payment for his labor work later
19/01/1989