25/03/1988
Financial, Payment Due

Two progress bills addressed to Oliver & Co. for the specialty works C.E.S. had been executing in the project as a subcontractor. The first progress payment is dated 25-Feb-89 and the second 25-Mar-89; both list eight subcontracts, the amount of each contract, the previous darws, the percentage of work completed and the requested draw amounts.

Authors:
Christopher Alexander, Center for Environmental Structure, Berkeley, CA, U.S.A.