The Julian Street Inn – Shelter for the Homeless: C.E.S. application for progress payment for subcontracting specialty construction works
25/03/1988Two progress bills addressed to Oliver & Co. for the specialty works C.E.S. had been executing in the project as a subcontractor. The first progress payment is dated 25-Feb-89 and the second 25-Mar-89; both list eight subcontracts, the amount of each contract, the previous darws, the percentage of work completed and the requested draw amounts.