The Julian Street Inn – Shelter for the Homeless: Cost estimates by the Oliver & Co.

31/07/1987
Financial, Cost Estimate

Five studies with contractor’s estimated costs by trade for the whole project, including progressively updated calculations between the months of January and July. Handwritten notes and editing are included.

Authors:
Maxim D. Schrogin, Oliver & Company Inc., Berkeley, CA, U.S.A.